VicSmart planning permits for two to four dwellings

Townhouse, unit and dual occupancy projects of up to four dwellings can now use VicSmart, the planning system's fast-track permit process, where the site and the design qualify. We check whether your project can use it and prepare the application.

What changed

Three amendments to Victoria's planning schemes sit behind this:

  • March 2025, Amendment VC267. Introduced the Townhouse and Low-Rise Code (Clause 55), a set of standards for developments of up to three storeys. A design that meets a standard is taken to meet the objective behind it.
  • October 2025, Amendment VC288. Opened VicSmart to applications for two dwellings on a lot.
  • October 2026, Amendment VC319. Raised the limit from two dwellings to four.

A VicSmart application is not advertised to neighbours, and neighbours cannot appeal council's decision to VCAT. The decision period set for council is 10 business days.

Does your project qualify?

The main requirements are:

A residential zone. The land is in the General Residential, Neighbourhood Residential, Residential Growth, Housing Choice and Transport, Mixed Use or Township Zone. The Low Density Residential Zone is not included.

Four dwellings or fewer. No more than four dwellings on the lot in total, counting any existing dwelling that stays. Adding a dwelling behind an existing house is covered, as is extending a dwelling on a lot that already has two or more.

Three storeys or less. The pathway relies on the Townhouse and Low-Rise Code, which covers development of up to three storeys.

The design meets 13 standards in the code. In plain terms, they cover:

  • the setback from the street and the height of any front fence
  • building height and how much of the site is built on
  • setbacks from side and rear boundaries, and walls built on boundaries
  • driveways and crossovers
  • tree canopy
  • the effect on neighbours: daylight and sunlight to their windows, shadows on their backyards and solar panels, and overlooking.

No other permit needed. The only permits required are ones the planning scheme lists for VicSmart. If an overlay or another control triggers a permit of its own, such as a heritage or flooding overlay, the application will usually follow the standard process.

No covenant breach. The proposal would not breach a restrictive covenant registered on the title.

If any one of these is not met, the application goes through the standard process, which can involve public notice and objections. Get in touch to discuss your site.

How it works with your residential zone

VicSmart changes how an application is assessed. It does not switch off the zone.

Height and garden area. The zone's maximum building height and any minimum garden area requirement still apply.

Zone schedules. A schedule to the zone can set its own requirements for matters such as street setback, site coverage and front fence height. Where it does, those are the requirements the design has to meet.

Different zones, different limits. Height and site coverage limits are generally tighter in the Neighbourhood Residential Zone than in the General Residential Zone, so a design that qualifies in one may not in the other.

The rest of the code. Council still assesses the application against the rest of the Townhouse and Low-Rise Code, including private open space, car parking location and storage.

How we help

  • Check whether the site can use VicSmart: zone and schedule, overlays and covenants.
  • Test the design against the standards with your architect or building designer, before the plans are finalised.
  • Where a design is close, advise on what would need to change to qualify, or whether the standard process is the better route.
  • Prepare and lodge the application, and deal with council through to its decision.

Project outside VicSmart? See planning permits for homes and multi-unit developments.

Common questions

Is a VicSmart application decided in 10 business days?

Ten business days is the decision period set for VicSmart applications. It applies to applications that qualify and include the information council needs. Whether yours qualifies depends on the site and the design.

What if the design doesn't meet one of the standards?

The project can still be applied for, but not through VicSmart. It goes through the standard process, which can involve public notice. Often a change to the design brings a project back within the standards. Get in touch to discuss your plans.

Does VicSmart cover subdivision?

Subdivision is a separate application with its own rules, and the right timing depends on the project. Get in touch to discuss your site.

This page is general information only. Planning controls differ from site to site, so get advice on your property before you commit.